There are four basic steps to earned value management:
  • Do your budget, usually by doing a WBS  to identify all the elements and the costs associated with each. This gives us a total project budget
  • Schedule the activities to give costs phased over time. Baseline this – it is your BCWS. Plot this by reporting period as a cumulative figure. This usually gives the typical S-curve graph.
  • For a given reporting period or status date, collect actual costs to date (ACWP). Identify the activities that have been completed and total the original budget for each of these activities to give a total earned value (BCWP). For each reporting period ad these two figures to your graph. There is a variety of ways to treat the partially complete activities on the reporting date.
The 0/100 method – only allowed to include if finished
The 50/50 method – can count half the original budget when started, all when finished
The 25/75 method - 25% when started, all when finished
And any variation in between but usually that’s too much work so keep it simple.
  • Report and analyse (e.g. look at EAC projection etc.)
Plot the graphs of cumulative BCWS, BCWP and ACWP. Also worth plotting CPI and SPI to spot and trends (are they getting steadily worse or better?).

One more thing to look out for is scope change (ie change to original BCWS). This is agreed changes that either add or remove budget. For an agreed scope change add or remove the activity costs from the period(s) that they occur in. Where added they become earned once done as per step 3.

One more thing to note; Studies show that CPI stabilises once you 15% into a project (i.e. if you have been too optimistic in the first 15%, you have been consistently too optimistic) and often gives an accurate EAC from then on.
CPI = {BCWP / ACWP}
< 1 means that the cost of completing the work is higher than planned (bad)
= 1 means that the cost of completing the work is right on plan (good)
> 1 means that the cost of completing the work is less than planned (good or sometimes bad).
Having a CPI that is very high (in some cases, very high is only 1.2) may mean that the plan was too conservative, and thus a very high number may in fact not be good, since the CPI is being measured against a poor baseline. Management or the customer may be upset with the planners since an overly conservative baseline ties up available funds for other purposes, and the baseline is also used for manpower planning.
SPI = {BCWP / BCWS } or
SPI = {EV / PV} - greater than 1 is good (ahead of schedule)


KENRICK DOOKIE
# 12 Sunset Drive,
Green Vale, Cunupia.
Trinidad. West Indies.
kenrickdookie@hotmail.com